Abstracts - faqs.org

Abstracts

Science and technology

Search abstracts:
Abstracts » Science and technology

Notice provisions must be followed

Article Abstract:

Notice provisions furnish project owners with the chance to eliminate or mitigate the impact of unexpected issues encountered by contractors and are typical in construction contracts. Failure to comply with the contract's notice requirements may bar contractors from obtaining financial relief from such occurrences. A court case involving a contractor and the Army Corps of Engineers will show that the consequences are extreme if contractors fail to adhere to notice provisions and unfairly placing owners at a disadvantage, whether or not courts require strict compliance with such provisions.

Author: Loulakis, Michael C., Santiago, Simon J.
Publisher: American Society of Civil Engineers
Publication Name: Civil Engineering
Subject: Science and technology
ISSN: 0885-7024
Year: 1999
Engineering

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA


Payment bond covers delay damages

Article Abstract:

An appellate court has ruled the delay damages are recoverable under a payment bond even when the contractor is only partially at fault for the delay. The ruling stemmed from the case filed by Consolidated Electrical and Mechanicals Inc. against Biggs General Contracting Inc. Biggs was the prime contractor in the renovation of the Missouri Air National Guard buildings at St. Louis International Airport. Consolidated was the subcontractor that installed the electrical fixtures and equipment on the project.

Author: Loulakis, Michael C., Santiago, Simon J.
Publisher: American Society of Civil Engineers
Publication Name: Civil Engineering
Subject: Science and technology
ISSN: 0885-7024
Year: 1999
Construction industry, Construction, Building

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA



Subjects list: Interpretation and construction, Contracts
Similar abstracts:
  • Abstracts: Noah's flood? Painters' atoms. Molecular crayons and mustard seed avalanches
  • Abstracts: Discussion by Tien H. Wu, fellow, ASCE, and Walter E. Hanson, honorary member, ASCE. Closure by Akram N. Alshawabkeh, associate member, ASCE
  • Abstracts: Owners' 'bad faith' can relieve contractors of notice requirements. Warranty of specification-shifting risk to the contractor
This website is not affiliated with document authors or copyright owners. This page is provided for informational purposes only. Unintentional errors are possible.
Some parts © 2025 Advameg, Inc.