Foresite

Article Abstract:

The lead times of UK construction industry trade packages are monitored to analyse the procurement times involved in obtaining products within the industry. The lead time of bespoke cladding has increased by 20% from April 1998 to June 1998, giving a lead time of 17 weeks. Lead times of uninterruptible power supplies increased from 3 weeks to 13 weeks from April 1998 to June 1998 while drylining materials usually took about 8 weeks. The survey highlighted the demand within the industry but the failure of suppliers to keep up with demand.

Publisher: Builder Group plc
Publication Name: Building
Subject: Construction and materials industries
ISSN: 0007-3318
Year: 1998
Construction equipment

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA


Foresite

Article Abstract:

Procurement lead times in the UK construction industry are generally lengthening, reflecting the fact that the industry's workload is rising. In control and building management systems, lead times have lengthened by between two and 16 weeks, while lead times for ductwork have increased by one week to 10 weeks, despite seven-day-a-week production in this sector. The average lead time for structural steel is 12 weeks, while the lead time for curtain-walling has increased by 30% to 30 weeks.

Publisher: Builder Group plc
Publication Name: Building
Subject: Construction and materials industries
ISSN: 0007-3318
Year: 1998
Analysis, Purchasing

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA


Foresite

Article Abstract:

There is currently no trend in lead times within the construction industry, although 50% of those questioned forecast increased work over the next 6-12 months, according to data compiled by QS Gardiner & Theobald and Mace. Lifts currently have a lead time of 29 weeks; while ductwork stands at 10-12 weeks; and escalators at 20 weeks. Details of trends in enquiry levels, tender prices and orders are also given.

Publisher: Builder Group plc
Publication Name: Building
Subject: Construction and materials industries
ISSN: 0007-3318
Year: 1995

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA


Subjects list: Construction industry, Equipment and supplies, Surveys, Lead time
Similar abstracts:
  • Abstracts: Foresite
  • Abstracts: Western report. part 6
  • Abstracts: Nouvelle cuisine. Housemaster. The knight's tale
  • Abstracts: Making the best choices for your digital needs: part 2. How high is up? Managing turnover of the sales staff
  • Abstracts: Is Egan on target? All risks policy. New CIC chief awaits Egan challenge
This website is not affiliated with document authors or copyright owners. This page is provided for informational purposes only. Unintentional errors are possible.
Some parts © 2025 Advameg, Inc.